Malaysia Open DC Project: 100KW Air-Cooled Precision Air Conditioning Solution

Malaysia Open DC Project: 100KW Air-Cooled Precision Air Conditioning Solution

2026-01-22

I. Client Introduction

Open DC Malaysia is a well-known cloud service network technology company in Malaysia, specializing in providing professional server storage services for clients. Its data center is a key carrier supporting core business operations, imposing strict requirements on the temperature control stability, adaptability and installation flexibility of industrial equipment. To upgrade the existing data center, the client sought foreign trade equipment and customized solutions suitable for the scenario.

II. Project Background and Pain Points

The client was retrofitting its existing data center and needed room-level air-cooled air conditioners to meet the cooling needs of new equipment. However, the data center suffered from small space and outdated facilities. Conventional precision air conditioners, with fixed volume, could not be carried in smoothly for installation and were difficult to adapt to the site layout, becoming a core obstacle to the renovation project. There was an urgent need for commercial equipment with flexible installation characteristics to solve the dilemma.

III. Customized Equipment Solutions

To address the client's space constraints and cooling needs, we provided a customized solution of CyberMaster series precision air conditioners for large server rooms, configuring 2 units of 100KW air-cooled room-level precision air conditioners as core foreign trade equipment. This series of equipment adopts a modular design, which can be transported in parts and assembled on-site, perfectly adapting to the installation needs of small spaces. Meanwhile, it features precise temperature control, providing stable climate guarantee for the IT environment, balancing installation flexibility, operational stability and cooling efficiency, and fully meeting the client's renovation and upgrading demands.

IV. On-Site Execution and Support

We set up a professional technical team to provide full-process on-site services in Malaysia. Combined with the small space characteristics of the data center, we formulated a modular installation process, transported the equipment in parts, then conducted precise assembly and commissioning, avoiding installation difficulties caused by space limitations. Simultaneously, we carried out operation training for the client's technical personnel, explaining the maintenance points, temperature control adjustment skills and fault diagnosis methods of modular equipment, helping the client quickly master operation and maintenance capabilities.

V. Project Achievements and Long-Term Cooperation

At present, 2 units of 100KW air-cooled precision air conditioners have been fully installed, debugged and put into use. The modular design successfully solved the installation problem of small space. The precise temperature control and stable operation performance of the equipment fully meet the client's expectations, building a reliable cooling environment for the renovated data center. The project achievements have been highly recognized by the client. With scenario-adaptable customized solutions, high-quality foreign trade equipment and professional services, it lays a foundation for long-term cooperation between the two parties in subsequent data center equipment upgrading projects.